Channel Normalization on Jl Percetakan Negara VB to Complete June

Channel normalization on Jalan Percetakan Negara VB, RT 06 and 07 of RW 03, Rawasari Urban Village, Cempaka Putih, Central Jakarta is targeted to complete this mid June.

Now the progress has reached 90 percent

Cempaka Putih District Water Resource Implementer Unit Head, Sahudi explained the 336 meters-long water channel is being normalized since February ago by using u-ditch concrete.

"Now the progress has reached 90 percent. It is targeted to complete this mid June," Sahudi said, Monday (6/2).

Arrangement of Jalan Bukit Duri Utara Raya Area Reaches 90 Percent

According to him, the normalization is run to accommodate resident aspiration.

"The channel was unable to flow water smoothly. It triggers inundation," he added.

Roland (48), one of local residents, appreciated the channel normalization. He hopes it will eliminate the inundation during the heavy rain.

"Hopefully it can be completed on time to avoid inundation during rainy season," he hoped.

Linked News
Popular News indeks
  1. Public Urged to Use Public Transit for GBK Events to Avoid Heavy Traffic

    access_time05-06-2026 remove_red_eye1311 personAldi Geri Lumban Tobing
  2. Traffic Measures Prepared to Ease Congestion Around GBK This Weekend

    access_time04-06-2026 remove_red_eye1226 personAldi Geri Lumban Tobing
  3. Central Jakarta Government Responds Quickly to Fire Victims in Tanah Tinggi

    access_time04-06-2026 remove_red_eye1037 personFolmer
  4. Pramono Launches Jumbo Biopores, Aims for Jakarta Waste Management Blueprint

    access_time07-06-2026 remove_red_eye967 personDessy Suciati
  5. Pram Inaugurates Matraman Health Center, Calls for Seamless Public Service

    access_time05-06-2026 remove_red_eye796 personDessy Suciati